BBC slammed by watchdog over failed DMI project
Eight months after the project was canned, government spending watchdog probes why.
The BBC's defunct Digital Media Initiative (DMI) failed because the executives overseeing it didn't ensure it was technically sound or fit for purpose, it has been claimed.
The project's aim was to create a tapeless digital production and archiving system to help the broadcaster's staff manage video and audio content from their desktops.
The initiative ran into difficulties, and was canned in May 2013, with the BBC concluding that much of the 125.9 million spent on the project had been wasted.
The CTO overseeing the project was suspended at the same time, before being sacked two months later.
Government spending watchdog, the National Audit Office (NAO), has released its assessment of what went wrong with the project.
It was originally due for completion in May 2009, with Siemens tasked with building the system, but the BBC terminated the contract in September 2009 and brought the development of DMI in-house.
Based on the report's findings, DMI's problems seem to stem from this, with the NAO concluding the BBC did not do enough to assess the value for money and risks involved with taking the project on.
Get the ITPro. daily newsletter
Receive our latest news, industry updates, featured resources and more. Sign up today to receive our FREE report on AI cyber crime & security - newly updated for 2024.
"The BBC's decision to take the DMI in-house was high-risk. It needed to fill capability gaps to complete the programme by recruiting staff with the right skills or using third parties to deliver DMI components," the report states.
It also states the BBC was "too optimistic" about its ability to implement the project, and didn't do enough to ensure it was fit for purpose.
That being said, the report acknowledges the aspects of DMI that were delivered were favourably received by users.
"However, as the project began to encounter further difficulty and delay, users lost confidence in the DMI to provide a reliable system that met their requirements," the report states.
"Some television production teams that relocated to the BBC's new site at Salford had to install alternative digital storage and adapt their editing technology to operate as standalone systems.
"As soon as this happened, the BBC's forecast of business benefits for a fully functioning DMI system started to erode," it added.
Furthermore, the NAO said the project was not scrutinised enough by the powers that be, with the organisation ruling the reporting arrangements used for DMI were not "fit for purpose".
"It is standard practice in technical design to commission thorough independent technical assessments. We noted in our previous report that the BBC had not obtained an independent technical assessment of its design," the report continued.
"The BBC did not take sufficient steps to implement our recommendation to complete an indendent technical assessment."
In a statement, Diana Coyle, vice chairman of the BBC Trust, said the broadcaster must use the DMI experience to shape its handling of future IT projects.
"As we announced last December, were are working with the executive to strengthen project management and reporting arrangements within a clearer governance system," Coyle said.
"This will ensure that serious problems can be spotted and addressed at an earlier stage."
Amyas Morse, head of the NAO, said the report highlights the fact the BBC did not have "sufficient grip" on the implementation of DMI.
"Nor did it commission a thorough independent assessment of the whole system to see whether it was technically sound," said Morse.
"If the BBC had better governance and reporting for the programme, it would have recognised the difficulties much earlier than May 2012."